Advance Design Consultants was contracted by Headway Technologies to Design an additional 12,000 sq. ft. onto the south-east corner of Building-1 located at 497 S. Hillview Drive, Milpitas, CA 95053.

ADC designed clean room improvements for a wafer manufacturing facility. The project included clean improvements and access between different classification areas, installation of
fire separation doors for H-7 and F-1 areas, installation of chemical storage areas. ADC designed the installation of multiple tools including but not limited to; Veeco PVDI System, Veeco Ru-CVD
System, Veeco IBD System, MRT2000 Magnetic Annealing Oven and FEI Certus FIBE Tools. These tools required the design of intricate chemical delivery systems.

New expansion area is composed of new Cleanroom Tunnels, Service Chase area, fire rated corridor for exiting, and auxiliary spaces to house storage or Electrical Rooms. The expansion was integrated into the existing structure including Structural and Architectural elements, but to support the new Mechanical and Ancillary Support equipment. Existing Utilities (Chilled Water, Hot Water, Process Cooling Water, Compressed Dry Air, Nitrogen, Process Vacuum, Deionized Water, Acid Waste, General and VOC exhaust) were extended to serve the new expansion area in preparation for the new tool install package. Adequacy of existing capacities were studied and evaluated by ADC. Due to the tight tolerance required by Headway, the Clean Aisle space was ISO Class 4 (Class 100) and designed to maintain 68 F +/- 2 F, and 45% RH +/- 5% on a 0.01% ASHRAE outside air design day at 105 F dry-bulb. The Electrical Distribution served the existing 12kV substation and distributed 480V switchgear to feed all new HVAC equipment, Cleanroom and Core, and prepare Power Distribution for new Manufacturing Tools. The building shell was expanded in order to support the additional space required.

Copyrights ©2018 - Advanced Design Consultants, INC.

 

Update to our Clients & Partners:

ADC is taking the COVID-19 situation seriously to protect the health and well-being of our employees, clients and partners.

Advance Design Consultants, Inc. has implemented a Work from Home Plan (WFH) program to ensure our staff can comply with Santa Clara County's Shelter-In-Place order while still conducting business. Our main office in San Jose is currently physically closed, however our staff continues to support normal business operations initiating WFH program yesterday. ADC’s staff will continue to work with our clients, partners, consultants and community to provide business continuity of the same services that you have come to expect from us.We are committed to continue to provide the architectural-engineering design and calculations services, communication, and collaboration needed to keep our projects moving ahead on schedule. As we all work through this difficult period of time fighting this world pandemic together we will ensure to update you on our progress and deliverables.

During this time, please use email as this is the best way to reach us. Continue to reach out to your direct contact, and if you do not have a direct contact, use info@adcengineers.com and your message will be routed to the appropriate person.

We want to thank everyone for understanding that ADC will do our best to deliver our projects on schedule to best of our abilities while performing these task from home. If you have any questions, concerns, comments or even just need someone to talk to concerning a current or future project, do not hesitate to contact us. Together we can all ensure business continuity for our region and beyond.

 

Update to our Clients & Partners:

ADC is taking the COVID-19 situation seriously to protect the health and well-being of our employees, clients and partners.

Advance Design Consultants, Inc. has implemented a Work from Home Plan (WFH) program to ensure our staff can comply with Santa Clara County's Shelter-In-Place order while still conducting business. Our main office in San Jose is currently physically closed, however our staff continues to support normal business operations initiating WFH program yesterday. ADC’s staff will continue to work with our clients, partners, consultants and community to provide business continuity of the same services that you have come to expect from us.We are committed to continue to provide the architectural-engineering design and calculations services, communication, and collaboration needed to keep our projects moving ahead on schedule. As we all work through this difficult period of time fighting this world pandemic together we will ensure to update you on our progress and deliverables.

During this time, please use email as this is the best way to reach us. Continue to reach out to your direct contact, and if you do not have a direct contact, use info@adcengineers.com and your message will be routed to the appropriate person.

We want to thank everyone for understanding that ADC will do our best to deliver our projects on schedule to best of our abilities while performing these task from home. If you have any questions, concerns, comments or even just need someone to talk to concerning a current or future project, do not hesitate to contact us. Together we can all ensure business continuity for our region and beyond.